KUALA LUMPUR: The Sewerage Services Department is taking immediate action to ensure that the Sewerage Pipe Network construction project (Package D44) worth RM393mil, which should have been completed in February 2018, will be finished as soon as possible.
Natural Resources and Environmental Sustainability Minister Nik Nazmi Nik Ahmad said the project, which started in 2014, was delayed because the contractor was having problems.
"I think the Sewerage Services Department is implementing immediate measures to complete the critical portions soon,” he said after launching the ForestONE application at a shopping mall on Friday (Dec 22).
Nik Nazmi was commenting on the project progress, which has yet to be completed even though the contractor had been given an extension until Nov 22 to finish it.
Package D44 is part of the River of Life Greater KL initiative that seeks to raise the quality of river water, focusing on controlling sewage pollution in the Bunus catchment area.
The scope of the project includes the design and construction of a 55km sewerage pipe network and the upgrading of two sewage pumping stations in areas under the jurisdiction of the Kuala Lumpur City Hall and the Ampang Jaya Municipal Council.