KUALA LUMPUR: Tenaga Nasional Bhd’s (TNB) RM4.2bil Ulu Jelai Hydroelectric project will further boost the national utility’s ability to meet the surge in demand at peak hours.
In a statement Tuesday, TNB said the new green energy power plant once completed in the third quarter of this year, its two units (2 X 186 Megawatt (MW)) would add another 372 MW to TNB’s hydroelectric generation capacity.
TNB hydroelectric generation was earlier boosted by the 250 MW of combined capacity from the Hulu Terengganu Hydroelectric project, which was fully commissioned in December 2015.
TNB’s total installed capacity from hydroelectric power plants currently stood at 2,161 MW. With the commissioning of Ulu Jelai, its total hydro installed capacity will be 2,533 MW.
As of June 2016, TNB has a 51.9% share of the electricity industry’s total installed capacity of 22,747.53 MW.
“Construction of the RM4.2bil Ulu Jelai Hydroelectric project started in 2011 and is currently more than 95% complete. Almost 750,000 cubic metres of concrete were used to built the dam using roller-compacted concrete (RCC) – a relatively modern method in the engineering world,” TNB said.
Located in Cameron Highlands, Pahang, the project features a 88 metres high dam with a crest width of 460 metres.
According to a report by the United Nations, the project will reduce around 250,000 tonnes of carbon dioxide equivalent per year by substituting conventional power generators that run on coal and other fossil fuels during peak periods.
Already a subscriber? Log in.
Cancel anytime. No ads. Auto-renewal. Unlimited access to the web and app. Personalised features. Members rewards.
Follow us on our official WhatsApp channel for breaking news alerts and key updates!