Atlantic’s biggest offshore wind turbine to rise this week in US


Offshore substation is expected to deliver electricity to shore in October. Source: Avangrid

NEW YORK: About 15 miles south of Martha’s Vineyard, Massachusetts, a massive structure emerges from the Atlantic Ocean. Nearby it will have the biggest turbines in the Atlantic, as tall as the Washington Monument with the Statue of Liberty stacked on top.

It’s the first offshore power substation in the United States and in October it is expected to start delivering electricity from Vineyard Wind, the nation’s first commercial-scale offshore wind farm.

By 2024, the project is expected to generate enough electricity to power 400,000 homes. A few miles away are the first six monopiles, foundations affixed to the seabed that will hold the turbines, which developers, Avangrid Inc and Copenhagen Infrastructure Partners, are set to begin attaching next week, said Sy Oytan, Avangrid’s chief operating officer for offshore wind.

“Seeing the first monopile in the water was such a relief,” Oytan said. “It was the point of no return.”

The monopiles are the most tangible sign of progress for US offshore wind, but they come at a time when the industry is struggling. While construction on Vineyard Wind is ramping up, other projects have been stalled after inflation and rising financing rates drove up costs.

Developers are seeking to renegotiate power-delivery contracts they signed years ago, before surging component prices made the deals unviable. And some states are balking at the prospect of higher electricity rates from offshore turbines.

That’s why Oytan is so pleased this project is finally taking shape.

Strong, consistent winds combined with shallow water make the United States northeast one of the best places in the world for offshore wind, said Oytan.

He was leading a tour of the site on the Captain John & Son II Wednesday, about two hours from Hyannis, Massachusetts, for about 75 lawmakers, environmental advocates, labour representatives and local community leaders. The 85-foot (26-meter) vessel was dwarfed by the substation, which is almost the size of a football field.

And that will look tiny compared to the 62 turbines that will be installed by early 2024. The General Electric (GE) Co systems will each have about 13 megawatts of capacity and will soar about 850 feet into the sky.

They will be the biggest in the Atlantic, according to Eric Hines, a Tufts University engineering professor. And GE is expected to introduce even taller versions of its Haliade turbines.

“This is real,” said Joe O’Brien, the political and legislative director for the North Atlantic States Regional Council of Carpenters. “Ten years ago it was hypothetical.”

O’Brien represents some of the union workers who are eager to see the industry take off, and deliver high-paying jobs to the region.

President Joe Biden has set a goal of 30 gigawatts of turbines in operation in US waters by 2030, and several northeast and mid-Atlantic states have established their own targets.

But those goals are threatened by the economic turmoil that’s beset the industry. Avangrid agreed in July to pay US$49mil to cancel a power-purchase agreement for its 1.2 gigawatt Commonwealth Wind project, saying rising costs had made it unviable. Vineyard Wind managed to avoid those issues because it lined up supply deals before inflation drove up costs.

These issues are temporary setbacks, according to industry advocates. Demand for clean energy will only increase, driven by the push to electrify more of the economy and the increasing urgency of the fight against climate change. That will spur more utilities to pursue offshore wind, especially in the Northeast where there are few alternatives, said Susannah Hatch, director of clean energy policy for the Environmental League of Massachusetts.

“There might be a little bit of a lull,” she said. “It doesn’t mean the industry isn’t moving forward.”

There are two wind farms in service in US waters now, one near Block Island, Rhode Island, that has five turbines and a total of 30 megawatts of capacity, and a two-turbine project in Virginia that has 12 megawatts of capacity.

Both are viewed as demonstration projects that laid the groundwork for larger projects like Avangrid’s 806-megawatt Vineyard Wind.

Besides the Avangrid project, another wind farm is under construction nearby, the 132-megawatt South Fork project east of Long Island, New York.

The smaller project is a joint venture of Eversource Energy, a Massachusetts utility, and Orsted AS, a Danish energy developer, will have 12 turbines. It began offshore work in June and will probably be complete before Vineyard, though Avangrid executives expect their project will be able to deliver electricity to the grid earlier.

The emergence of offshore wind projects has brought together disparate groups, said O’Brien, the union official. Labour groups and environmentalists historically have found themselves in opposition.

But looking around the deck of the Captain John & Son II, O’Brien pointed to the different groups of people who had all come to see the result of their years of effort promoting the offshore wind industry.

“Everyone wants this,” he said. “Now we’re all in the same boat.” — Bloomberg

Follow us on our official WhatsApp channel for breaking news alerts and key updates!

   

Next In Business News

Trading ideas: IOI, Gagasan Nadi, Xin Hwa, T7, TCS, Aneka, HE, Ann Joo, Aimflex, F&N
Toyota likely to post first profit drop in two years
Strong financial grasp critical for investors
Licence freeze to have impact on Xin Hwa
Gagasan Nadi in RM185mil acquisition
Proton October sales climb 13.6% to 12,799 units
Aneka Jaringan wins RM39mil job
TCS bags RM86mil contract
The Philippines to be cautious in policy easing cycle
Ringgit maintains stronger footing at the close

Others Also Read