Court: No power to grant extension


Take them to task: According to the liquidated damages clause, condo buyers can claim 10 per annum of the purchase price for the delay.

KUALA LUMPUR: The Housing Controller has no power to grant an extension of time to developers who delay the completion of housing projects, the High Court has ruled in a landmark judgment.

This means a housing developer has to pay compensation to the affected buyers for delays in the delivery of vacant possession.

Subscribe or renew your subscriptions to win prizes worth up to RM68,000!

Monthly Plan

RM13.90/month

Annual Plan

RM12.33/month

Billed as RM148.00/year

1 month

Free Trial

For new subscribers only


Cancel anytime. No ads. Auto-renewal. Unlimited access to the web and app. Personalised features. Members rewards.
Follow us on our official WhatsApp channel for breaking news alerts and key updates!

News , bureaus

   

Next In Nation

MPV in crash where eight died was being pursued by cops
Melaka carrying out measures to protect residents from crocodile threat
Malaysia re-elected to Uncitral for 2025-2031 term
Malaysia, Vietnam elevate bilateral relations to comprehensive strategic partnership
Vehicles in viral video given summonses for parking too close to bus stop, Ipoh cops say
Eight people in MPV die in collision with 4WD in Sibu
Company director loses RM34,000 in scam to supply non-existent Agriculture Department order
Girl among three killed, baby hurt after family of four on motorcycle crash into lorry
Water levels at three major Kelantan rivers surpass alert levels
Scheduled water cuts to seven Penang Island areas Nov 28-29

Others Also Read