Salvage operation: A resident’s car being lifted from the sinkhole in Taman Wawasan, Puchong. Once the iron pile installation work is completed, the process of restoring the slope to its original structure will be carried out before proceeding with road-levelling works. — Bernama

PUCHONG: Works to instal iron piles to stabilise soil movement in the landslide area along Jalan Wawasan in Taman Wawasan here is expected to be completed within four days.

Subang Jaya mayor Datuk Mohd Fauzi Mohd Yatim said to date, a total of 121 out of the 375 iron piles, had been placed.

“After the installation is completed, the process of restoring the slope to its original structure will be carried out before proceeding with road-levelling works,” he told Bernama here yesterday.

He said the cause of the landslide, which struck last Saturday, was still being investigated by the Minerals and Geoscience Department.

The occupants of nine terraced houses in the residential area were ordered to evacuate following the landslide.

   

Next In Nation

Thunderstorms expected in 11 states, three FTs till 7pm tonight, says MetMalaysia
Legendary composer Ahmad Nawab laid to rest
Najib fails to permanently stay RM6.6bil CBT trial
GISB: Seven of 12 investigation papers brought to court, says Aminuddin
Motorcyclist killed in crash on Jalan Skudai, police investigate illegal parking touts in separate operation
BCS says no logging taking place at Tongod cement factory site
RM9.1mil in traffic summonses paid during anniversary celebration event
Three in family killed in early morning Bandar Permaisuri car crash
Immigration Dept to introduce special digital pass from January
Doctor loses over RM130,000 in online investment scam

Others Also Read