Iron pile installation almost done


Salvage operation: A resident’s car being lifted from the sinkhole in Taman Wawasan, Puchong. Once the iron pile installation work is completed, the process of restoring the slope to its original structure will be carried out before proceeding with road-levelling works. — Bernama

PUCHONG: Works to instal iron piles to stabilise soil movement in the landslide area along Jalan Wawasan in Taman Wawasan here is expected to be completed within four days.

Subang Jaya mayor Datuk Mohd Fauzi Mohd Yatim said to date, a total of 121 out of the 375 iron piles, had been placed.

“After the installation is completed, the process of restoring the slope to its original structure will be carried out before proceeding with road-levelling works,” he told Bernama here yesterday.

He said the cause of the landslide, which struck last Saturday, was still being investigated by the Minerals and Geoscience Department.

The occupants of nine terraced houses in the residential area were ordered to evacuate following the landslide.

Follow us on our official WhatsApp channel for breaking news alerts and key updates!
   

Next In Nation

Do you know...about nutmeg?
Selangor cops confirm receiving reports on deaths linked to New Year's Eve concert
Mat rempit ‘trapped’ by cops during traffic ops
Debris a danger to motorists
Johor civil staff get extra holiday
The long-awaited Health Service Commission can help tackle manpower issues, say experts
Uncertainties fuel govt doctor exodus
Hoping for a reunion with sister Anita Sarawak in Vegas
PETRONAS DRIVES ENVIRONMENTAL CARE IN SOUTHERN REGION
Tony Leung ‘not appearing’ in third season of Squid Game

Others Also Read