MRT3: Land acquisition process to start in stages next year


PUTRAJAYA: MRT Corp will begin its land acquisition process in stages from next year for the Mass Rapid Transit Line 3 (MRT3) Circle Line project, which will take two years to be finalised, says Transport Minister Anthony Loke.

Speaking at a media conference after the Lease Agreement signing ceremony between MRT Corp and the Federal Lands Commissioner (PTP) here on Thursday (Dec 21), Loke said that to minimise the cost of land acquisition for the government, MRT Corp would actively cooperate with property developers to integrate the MRT3 stations.

"I would like to state here that the government has approved the allocation for the process of land acquisition for the MRT3 project.

"Our approach towards the land acquisition process will combine prudent and courteous measures to ensure minimal social impact on the community," he said.

Without giving any details on the amount allocated for that purpose, Loke said the acquisition process is expected to involve 1,012 lots of land covering 842 private lots of land, government land (133 lots) and unknown land (37 lots).

"As we have said, there is a mechanism to minimise the cost for the government and we are also open to discussions with landowners," he said, adding that the alignment for MRT3 had yet to be finalised.

Regarding the lease agreement, Loke said the interest of the Unity Government through PTP and MRT Corp would be guaranteed, especially in ensuring that regulation and asset management were more efficient and the reserve areas along the MRT alignment were properly monitored.

"This will enable MRT Corp to implement spillover development that can provide commercial returns and make sure the people will benefit from the provision of public facilities at MRT station areas," he said.

Earlier, Loke and Minister of Natural Resources and Environmental Sustainability Nik Nazmi Nik Ahmad witnessed the signing ceremony, which was officiated by Department of Lands and Mines director-general Datuk Muhammad Azmi Mohd Zain and MRT Corp chief executive officer Datuk Mohd Zarif Hashim.

The agreement was for the existing route, namely the Kajang and Putrajaya MRT lines. - Bernama

MRT3 , Loke , Lease Agreement , Nik Nazmi , MRT Corp , PTP ,

   

Next In Nation

Efforts being made to rebrand industrial training institutes, deputy minister tells Parliament
Number of flood victims in three states remains unchanged as of 8am
SPM exams to kick off Dec 2, end on Feb 6, 2025
Putrajaya ordered to return seized Swatch watches
Kluang motorcyclist killed after losing control of machine, crashing into streetlight
Anwar, Yoon hold talks on Malaysia-South Korea ties
UPSI lecturer wins prestigious GESS Award for VR teaching project
Teacher feared drowned while fishing in Sungai Pahang
Law on fake info, RFID inefficiencies among focus of Parliament today
Mohd Hanis family to seek legal action after fatal collision with reversing lorry in Bangsar

Others Also Read