RM24mil Labuan healthcare staff quarters project contract terminated due to delay, says Ahmad Maslan


LABUAN: The Labuan healthcare staff quarters project, costing RM24 million, has reached a standstill as the contractor failed to adhere to the agreed-upon work schedule, said the Deputy Works Minister.

Initiated in early 2022, the project's progress has lagged significantly, reaching only 23% completion with a 31% delay.

Datuk Seri Ahmad Maslan expressed the necessity of terminating the contract, citing the project's crucial importance to healthcare staff in Labuan.

"The contract, awarded on Dec 1, 2022, will now undergo a retendering process, with an anticipated increase in project costs overseen by the Economic Planning Unit.

"The project was initially awarded at RM24mil. Certainly, after the retendering process, the cost will be increased," he said after the handing over ceremony of the Upgrading Existing Space into Sterile Pharmacy Project at Labuan Hospital.

The deputy minister said the project was initially slated for completion on June 29, 2023. Now, It faces an uncertain timeline, with its progress halted in January 2024.

The Labuan healthcare staff quarters project is situated on an eight-acre site in Membedai Jalan Tanjung Teras, adjacent to the Membedai Health Clinic and Labuan Health Department headquarters.

The project consists of four units of class D semi-detached houses, one five-storey apartment block (Block F) with 18 units, and another five-storey block (Block G) with 16 units.

In a positive development, Ahmad Maslan commended the Labuan Public Works Department and the contractor for the timely completion of the RM6.6mil Upgrading Existing Space into Sterile Pharmacy Project at Labuan Hospital.

Meanwhile, Ahmad Maslan also addressed the delayed RM26.8mil Bebuloh Health Clinic project, initiated in Nov 2019.

"After being retendered, a new contractor has been appointed, with a projected completion period of 156 weeks, targeting January 2027," he said.

The health clinic, originally part of the 10th Malaysia Plan, has transitioned to the 11th Malaysia Plan and would comprise the main building and 16 units of class F quarters. It aims to provide Type 5 health services, including pharmaceutical and dental services, a sick bay, outpatient treatment, and maternal and paediatric healthcare services. – Bernama

Follow us on our official WhatsApp channel for breaking news alerts and key updates!
   

Next In Nation

Anwar meets economist Jeffrey Sachs, discusses green energy, Asean
Baby among six killed in three-vehicle pile-up on Semporna-Tawau road
Kelantan to table syariah enactment amendments in July, says Deputy MB
Ampang abuse case: Police seize blunt objects from dead 7-year-old's mother, boyfriend
18 injured after express bus overturns near Kanowit in Sibu
Harimau Malaya development allocation raised to RM30mil, says PM
MACC obtains remand extension for three suspects in heavy vehicle inspection case
Anwar to visit UK after UAE, set to meet British PM Keir Starmer
Dr Wee urges action as Johor poultry farmers await over RM2mil in unpaid Covid-19 subsidies
Number of flood victims up by about 300 in Johor

Others Also Read