First phase of ECRL track installation ahead of schedule


KUANTAN: The track installation for the first phase of the East Coast Rail Link (ECRL) project, spanning from Kuantan Port City (KPC), Pahang, to Dungun, Terengganu, covering a distance of 92km, has been accomplished a month ahead of the projected schedule.

Malaysia Rail Link Sdn Bhd (MRL) chief executive officer, Datuk Seri Darwis Abdul Razak, attributed the achievement to the innovative 'CCPG-500A' track laying machine, marking a pioneering advancement in the nation's rail sector.

"On average, we managed to lay 1.5km to 2.0km of tracks per day, completing the KPC to Dungun stretch by the end of February, enabling full operation to commence at the beginning of March this year," he informed the media.

He was speaking during the ECRL Project Iftar ceremony held here last night, attended by state Public Works, Transportation, and Health exco, Razali Kassim, representing the Pahang Mentri Besar.

He stated that the ECRL track installation work has now entered its second phase since March 9, covering a mainline stretch of about 90km from KPC to Maran, Pahang.

Overall, the ECRL route spanning 258km in Pahang involves the construction of seven stations, including Cherating and KotaSAS for passengers only, while KPC, Paya Besar, Maran, Temerloh, and Bentong stations are combined passenger and cargo stations.

At the same event, 30 orphans and staff members from the Baitul Mukmin Welfare Organisation for orphans and the poor and Permata Al Insyirah Home for orphans and the poor were feted and presented with MRL donation cheques by Razali. - Bernama

Follow us on our official WhatsApp channel for breaking news alerts and key updates!

ECRL , Pahang , Terengganu , ahead , schedule , track installation , MRL

   

Next In Nation

Thunderstorm warning issued for eight states and Labuan
FashionValet: Vivy, husband to be charged on Dec 5
Home Ministry, UPM to introduce Malay language test for citizenship applications
Education Ministry placed 13,749 new teachers in schools nationwide, says Fadhlina
Landslide cuts off Orang Asli community in Pos Gob, Kelantan
Kluang woman nabbed for splashing hot water on 10-year-old daughter
Floods: TNB shuts down power substations to avert accidents
UPNM dual system may be restructured to prevent bullying, says Zambry
Floods: Number of evacuees drops to 72,620, Perlis fully recovers
Melaka to propose special financial aid for dialysis patients, says CM

Others Also Read