KUANTAN: The track installation for the first phase of the East Coast Rail Link (ECRL) project, spanning from Kuantan Port City (KPC), Pahang, to Dungun, Terengganu, covering a distance of 92km, has been accomplished a month ahead of the projected schedule.
Malaysia Rail Link Sdn Bhd (MRL) chief executive officer, Datuk Seri Darwis Abdul Razak, attributed the achievement to the innovative 'CCPG-500A' track laying machine, marking a pioneering advancement in the nation's rail sector.
"On average, we managed to lay 1.5km to 2.0km of tracks per day, completing the KPC to Dungun stretch by the end of February, enabling full operation to commence at the beginning of March this year," he informed the media.
He was speaking during the ECRL Project Iftar ceremony held here last night, attended by state Public Works, Transportation, and Health exco, Razali Kassim, representing the Pahang Mentri Besar.
He stated that the ECRL track installation work has now entered its second phase since March 9, covering a mainline stretch of about 90km from KPC to Maran, Pahang.
Overall, the ECRL route spanning 258km in Pahang involves the construction of seven stations, including Cherating and KotaSAS for passengers only, while KPC, Paya Besar, Maran, Temerloh, and Bentong stations are combined passenger and cargo stations.