Court: No power to grant extension


Take them to task: According to the liquidated damages clause, condo buyers can claim 10 per annum of the purchase price for the delay.

KUALA LUMPUR: The Housing Controller has no power to grant an extension of time to developers who delay the completion of housing projects, the High Court has ruled in a landmark judgment.

This means a housing developer has to pay compensation to the affected buyers for delays in the delivery of vacant possession.

Subscribe now and receive FREE sooka plan for 1 month.
T&C applies.

Monthly Plan

RM13.90/month

Annual Plan

RM12.33/month

Billed as RM148.00/year

1 month

Free Trial

For new subscribers only


Cancel anytime. No ads. Auto-renewal. Unlimited access to the web and app. Personalised features. Members rewards.
Follow us on our official WhatsApp channel for breaking news alerts and key updates!

News , bureaus

   

Next In Nation

Penang tunnel project studies incomplete due to port expansion plans
US court sentences M'sian 'Fat Leonard' sentenced to 15 years for corruption
Morning thunderstorms forecast in some states, including Selangor and KL
INTERACTIVE: Malaysia’s treasure trove of metals and minerals
Nearly 32,000 motorbikes inspected in four days
AWS IS BUILDING LOCAL, AND GOING GLOBAL
Committed to a greener future
Third BSI pedestrian route proposal stalls
Police op reduces motorcycle accidents by 10.1%
MACC officer charged with misusing seized funds

Others Also Read